How to Write an RFQ for Aluminum Windows, Doors, and Curtain Wall from a China Manufacturer

November 10, 2026 by moojiwall

How to Write an RFQ for Aluminum Windows, Doors, and Curtain Wall from a China Manufacturer

An RFQ for aluminum windows, doors, or curtain wall should give a manufacturer enough information to define the product, establish the technical basis, identify the deliverables, and quote a comparable commercial offer. The objective is not to describe every possible detail in the first message. It is to remove ambiguity at the stage where scope, performance, and commercial assumptions are agreed.

For overseas buyers, the most effective RFQ is usually a structured package rather than a single email. Drawings, schedules, specifications, finish samples, project logistics, and commercial terms should be referenced consistently. If two manufacturers interpret the same request differently, their quotations will not be directly comparable, even when the prices appear to be.

This guide explains the information a Foshan aluminum window, door, curtain wall, or sunroom manufacturer typically needs to prepare a meaningful quotation. It also identifies where project-specific evidence should be requested and how to separate product requirements from procurement assumptions.

Why Vague RFQs Lead to Inaccurate Quotes

A request such as “Please quote for 300 aluminum windows with glass and hardware for our project” identifies a product type and quantity, but it leaves nearly every decision open. The manufacturer may have to assume the opening size, frame profile, glass build-up, finish, hardware, test requirements, packing method, delivery scope, and installation responsibilities. Each assumption affects cost, production time, and risk.

The most common causes of non-comparable quotations include:

  • Incomplete opening and quantity schedules: sizes are missing, duplicated, or supplied as rough dimensions without indicating whether the dimensions refer to the structural opening or finished opening.
  • Undefined performance: the RFQ requests “thermal break” or “energy-saving glass” without stating the applicable project criteria, test configuration, or required supporting evidence.
  • Generic material descriptions: aluminum alloy, profile depth, wall thickness, glass type, sealant, hardware brand, and insulation assumptions are not distinguished.
  • Unclear finishes: powder coating, anodizing, fluoropolymer coating, wood-grain finishes, and pre-finished panels can have different appearance, durability, and coating requirements.
  • Contradictory documents: the drawing, specification, and email contain different requirements, but no document is identified as the governing source.
  • Missing logistics: port, destination, packaging, unloading, installation, and warranty responsibilities are left until after the quotation is accepted.
  • Unstated commercial assumptions: the quote does not state the Incoterm, payment schedule, validity period, production lead time, or exclusions.

A useful principle is to distinguish three levels of information: confirmed requirements, items to be clarified, and stated exclusions. A quotation should not appear to include an unconfirmed option. Instead, it should identify alternatives or exclusions so that the buyer can make an informed decision.

Required Documents for a Complete RFQ

A complete RFQ normally combines a written scope with project-specific drawings and schedules. The manufacturer’s manufacturing capabilities and project coordination resources can help buyers assess whether the request is sufficiently defined for quotation and production planning.

1. Drawing and opening schedule

Provide dimensioned drawings and a schedule that identifies, at minimum:

  • Product type and mark for each opening;
  • Overall width and height;
  • Structural opening or rough opening dimensions;
  • Frame depth, visible profile, and configuration;
  • Opening direction, sash arrangement, and operable panel positions;
  • Fixed, operable, transom, sidelight, or curtain-wall designation;
  • Glass make-up and any special panes;
  • Perimeter and intermediate mullion locations;
  • Interfaces with walls, slabs, roofs, waterproofing, and adjacent finishes;
  • Installation tolerances and movement requirements;
  • Design responsibility for structural, thermal, acoustic, and water performance.

Mark the schedule as preliminary, issued for quotation, or issued for construction. If dimensions are not final, state the permitted range and explain whether the quotation is based on an average size or a unit rate. Changes in size can affect glazing, hardware, reinforcement, weight, and packaging.

2. Project specifications

Include the relevant project specification sections rather than sending an entire specification without highlighting the requirements. A focused scope should cover:

  • Design and performance criteria;
  • Aluminum alloy and profile requirements;
  • Thermal-break or non-thermal-break construction;
  • Glass, insulating units, spacers, and sealant;
  • Hardware, locks, handles, hinges, rollers, and accessories;
  • Finishes and coating systems;
  • Sealant, gaskets, flashings, and interface components;
  • Installation, anchorage, and perimeter conditions;
  • Testing, inspection, documentation, and warranty requirements;
  • Applicable project standards and the required evidence.

When the project is at an early stage, ask the manufacturer to list assumptions and exclusions. For example, the RFQ may permit several glass alternatives, but it should explain who selects the final make-up and how changes are priced.

3. Quantity and delivery schedule

Break quantities down by product type, size, finish, glass configuration, and location. Provide both total quantities and a delivery or installation sequence if the project is phased. If some areas are added later, identify the likely revision period and state whether pricing is held for those areas.

A realistic delivery schedule should allow for engineering review, approved samples, production, inspection, packaging, shipping, customs clearance, and site receipt. Do not describe the factory lead time as the complete project delivery time.

Performance and Standards Language

Performance requirements should be written as project-specific criteria. Avoid treating a reference standard as proof that a particular product or project assembly meets the project’s needs. Standards are useful frameworks, but the buyer should request evidence for the proposed configuration.

RFQ requirement Information to state Evidence to request
Thermal performance Required U-value, SHGC, VT, or local energy criteria, including the applicable calculation boundary Project-specific calculations, test reports, or supporting technical data for the proposed assembly
Air and water performance Design pressure, water penetration resistance, air leakage limit, and installation conditions Relevant test reports and a statement of the tested configuration
Structural adequacy Wind load, dead load, deflection, span, support conditions, and design responsibility Engineering calculations, test results, or project-specific structural review
Acoustic performance Required sound reduction and test conditions Test evidence applicable to the selected glass and frame build-up
Fire or life safety Applicable building, opening, assembly, and testing requirements Documentation for the proposed product and the authority having jurisdiction
Quality assurance Inspection plan, factory inspection access, nonconformance process, and document list Inspection and quality-control procedure for the order

Depending on the market and application, buyers may reference NFRC, ENERGY STAR, CE, CSA, AAMA, ASTM, EN, AS 2047, or other local requirements. These references should not be presented as automatic certification of every offered product. State instead: “Please provide project-specific evidence demonstrating how the proposed assembly satisfies the stated requirement.”

Requesting a test report is not enough by itself. Check the applicant, product model, dimensions, configuration, glazing, installation conditions, test method, and report validity. If the proposed product differs materially from the tested assembly, ask the manufacturer to explain the engineering basis for the difference.

Materials, Finishes, and Hardware

An accurate RFQ defines what must be supplied without unnecessarily restricting the manufacturer to one equivalent brand. For aluminum systems, the buyer should identify the required alloy, extrusion or finish condition, structural profile concept, thermal-break requirement, wall thickness where technically critical, and any project-specific approvals.

Aluminum and profile system

State whether the requirement applies to the complete system or to selected components. Include profile depth, face width, visible frame size, glass-to-glass or frame-to-glass appearance, drainage path, sealant joint design, and compatibility with adjacent systems. If profiles are supplied under a third-party system, identify whether the manufacturer is authorized to use them and what documentation will be provided.

Glass and insulating units

Specify the design intent and the information needed to price it:

  • Nominal thickness and configuration;
  • Low-E coating and surface positions, where applicable;
  • Argon or krypton filling, spacer type, and sealant;
  • Tempered, laminated, heat-strengthened, or other safety treatment;
  • Acoustic, solar-control, fire, security, or bird-safe requirements;
  • Edge treatment, setting blocks, and compatibility with the glazing system;
  • Whether the manufacturer supplies glass or the buyer;
  • Breakage responsibility and replacement procedures.

Do not ask only for “double glass.” Two insulating units with the same basic description can have different coatings, spacers, gas fills, edge seals, and price implications.

Finishes and color control

For powder coating, state the coating system, color reference, texture, gloss range, substrate, and required color-difference limits. For anodizing, identify the class, finish, thickness expectation, and appearance reference. For fluoropolymer or other architectural coatings, request the proposed system, film thickness, substrate preparation, standard color reference, and project-specific maintenance or warranty assumptions.

Provide physical finish samples or an approved finish reference when appearance is critical. A color code alone may not adequately communicate the expected appearance under site lighting.

Hardware and accessories

List the required functions: locking, latching, egress, concealed hinges, multi-point locking, restrictors, handles, rollers, guides, anchors, gaskets, setting blocks, and drainage components. Identify commercial brands only where compatibility, certification, or warranty is important. Otherwise, specify performance, function, finish, and the requirement for the manufacturer to submit proposed alternatives for approval.

Ask whether replacement hardware is available locally or through the manufacturer, and clarify which components are included in the hardware warranty.

Packing, Inspection, and Hold Points

The RFQ should describe how the order will be packed and checked before shipment. Include the following:

  • Protection method for glass, frame corners, finished surfaces, and hardware;
  • Individual carton, crate, rack, or container-loading requirements;
  • Maximum carton weight and dimensions;
  • Labels showing project, opening mark, quantity, product type, and handling direction;
  • Protection against moisture, abrasion, salt exposure, and impact;
  • Whether hardware is packed with each unit or shipped separately;
  • Accessories, sealant, installation instructions, and keys;
  • Requirements for export packaging and destination conditions;
  • Whether the buyer intends to appoint a third-party inspector.

Define hold points in writing. A practical sequence may include approval of shop drawings, samples, mock-ups, finish samples, hardware selection, glass details, test evidence, and a pre-shipment inspection. At each hold point, state who reviews the submission, the required response period, and whether production may proceed before approval.

Inspection should cover product dimensions, construction, finish, visible defects, glass, hardware operation, markings, packaging, and document completeness. For curtain wall, specify whether dimensional checks will be based on shop drawings, production samples, or site re-measurement. For windows and doors, include opening, closing, locking, sealing, and sash-operation checks.

Commercial Terms: Incoterms, Payment, and Lead Time

The commercial section should prevent the buyer from comparing a delivered-project price with an ex-works factory price. State the selected Incoterm, named place of origin, named destination, version, and responsibilities for export clearance, import clearance, taxes, duties, insurance, inland transport, unloading, and installation.

Confirm whether the quotation includes:

  • Engineering, shop drawings, samples, and mock-ups;
  • Testing or certification fees;
  • Export packaging or special crating;
  • Loading supervision and container seals;
  • Freight and insurance;
  • Installation, caulking, waterproofing, or site measurement;
  • Taxes, duties, and destination charges;
  • Third-party inspection and bank charges;
  • Training, spare parts, or warranty replacement units.

Define the proposed payment schedule, currency, beneficiary details, documentary requirements, and any conditions for release of final payment. Tie meaningful payments to clear events such as drawing approval, sample approval, production completion, inspection, and document handover. The RFQ should also request the quotation validity period and state whether price is fixed, subject to indexation, or dependent on final approved quantities.

Ask for a production lead time broken into engineering, sample approval, fabrication, inspection, and packing. Also state the required shipping date and the consequence of delayed approvals. If the project has phased openings, request separate production and shipment dates for each phase.

Sample RFQ Section Outline

The following structure can be copied into an RFQ and completed for each project:

  1. Project information: project name, location, buyer, designer, contractor, contact details, quotation due date, and required quotation validity.
  2. Scope of supply: product categories, quantities, system scope, installation responsibility, and expressly excluded work.
  3. Drawing and schedule references: current drawing revision, opening schedule, typical details, and order of precedence among documents.
  4. Performance requirements: thermal, air, water, structural, acoustic, fire, and durability criteria, with project-specific evidence requested.
  5. Material and system requirements: aluminum, thermal breaks, glass, gaskets, sealants, hardware, anchors, and accessories.
  6. Finish requirements: coating or anodizing system, color reference, sample requirements, and appearance tolerances.
  7. Engineering and submittals: calculations, shop drawings, samples, test reports, manuals, and approval schedule.
  8. Inspection and hold points: inspection access, pre-shipment inspection, defect categories, repair or replacement procedure, and nonconformance process.
  9. Packing and shipment: export protection, labels, container dimensions, loading plan, shipping documents, and delivery sequence.
  10. Commercial offer: itemized prices, alternatives, exclusions, Incoterm, payment schedule, production lead time, shipping estimate, and validity.
  11. Warranty and after-sales service: proposed warranty periods, coverage, exclusions, claim procedure, spare-parts availability, and technical support.
  12. Clarifications: listed assumptions, unresolved design decisions, requested alternatives, and items requiring buyer confirmation.

Buyers can use the technical resources library to support specification reviews, compare product requirements, and prepare more consistent vendor submissions. For projects involving installer or general-contractor coordination, review the guidance on overseas GC and installer facade coordination before fixing interface responsibilities.

FAQ

How much information is needed before requesting an aluminum window quote?

At minimum, provide product types, quantities, opening sizes, drawings or schedules, performance requirements, glass and finish intent, delivery destination, and commercial terms. If the design is incomplete, mark the RFQ as budgetary and request an assumptions-and-exclusions list.

Should the RFQ require a specific hardware brand?

Only when compatibility, certification, appearance, availability, or warranty makes the brand essential. Otherwise, specify the required function, operation, finish, durability, and approval process so the manufacturer can propose an equivalent product.

How can I compare quotations from different Chinese manufacturers?

Use the same drawings, schedules, performance criteria, finish references, packaging requirements, Incoterm, and delivery basis for every supplier. Request an itemized scope and a list of assumptions so differences are visible rather than hidden in the total price.

Should a buyer request samples before ordering?

Samples or mock-ups can be valuable for finish, color, hardware, profile proportions, and construction review. Define which samples are required, what they must demonstrate, who bears the cost, and whether approved samples become the production reference.

What should happen when final sizes change after quotation?

Use a written revision process. The manufacturer should confirm the effect on price, lead time, glass selection, hardware, packing, and compliance evidence before the change is accepted.

Prepare a Clear RFQ and Request a Comparable Quotation

A strong RFQ gives the manufacturer a defined technical and commercial basis while leaving room for qualified alternatives. Include the current drawings, identify the governing requirements, request project-specific evidence, document hold points, and state the Incoterm and payment assumptions clearly.

To discuss a window, door, curtain wall, or sunroom package, contact JUHEMZENITH through the project contact form. Email [email protected] or message WhatsApp at +86 136 9027 9982. Please include the project location, product scope, current drawing revision, required delivery date, and destination so the review can begin promptly.